What is a change directive?

Study for the Registered Roof Observer (RRO) Exam. Use our comprehensive quiz with flashcards and multiple choice questions, complete with hints and explanations. Prepare with confidence!

A change directive is a formal instruction utilized in construction projects when there is a disagreement regarding changes to the scope of work. It allows for adjustments to be made without the full consensus of all parties involved while ensuring that work can proceed. This mechanism is particularly useful when immediate action is needed, and while the details of the change order might still be negotiated.

The change directive serves to record the intent to make changes and the need to include those adjustments in the contract at a later time, after an agreement is reached on the specifics and cost implications. This helps prevent delays in the project schedule caused by disputes over the changes.

The nature of the other choices highlights the importance of reaching consensus. An agreement on a change order requires mutual consent, while a change directive is inherently utilized in situations where such consent is not yet possible. Therefore, it plays a critical role in maintaining project momentum amidst unresolved issues related to changes in the scope of work.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy